Migrate checklists from Jira Server/Data Center to Jira Server/ Data Center

If you and your team are moving from Jira Server to Jira Server, be sure - your checklists will be safely migrated as well.

Some general recommendations can be found in this article from the Atlassian team

https://confluence.atlassian.com/adminjiraserver/migrating-jira-applications-to-another-server-938846962.html

Instructions

  1. Prepare Backup on destination Jira Server. Go to System → “Import and Export” section → Backup manager → Backup

  2. Restore Jira data from Backup on Jira Server. Go to System → “Import and Export” section → Restore System → Restore Jira from backup

     

  3. Then install "Smart Checklist for Jira" on the server, go to addon "Settings" -> "Global Settings" and Start Migration
    Note: Make sure you have Smart Checklist older than 5.3+ and above version installed.

     

  4. Once migration is completed - Smart checklist values would be successfully migrated from an Issue Property to a new Data Storage (Database) and custom fields would be synced as well!

  5. Check if the migration was successful in Issue Search view by adding “Smart Checklist” custom field

     

  6. That’s it!